They partially shut the Chimaltenango bypass as a consequence of hazard from landslides – 2024-06-26 10:32:28

Given the hazard posed by the landslides on the Chimaltenango bypass, the authorities determined to make partial closures of the route alongside which 1000’s of automobiles journey day by day from the west to the capital or vice versa.

Within the followingnoon of this Tuesday, June 25, native authorities, the Nationwide Coordinator for Catastrophe Discount (Conred) and the Common Directorate of Highway Safety and Security (Provial) analyzed the scenario on that street, which was labeled as a “mega work” by former president Jimmy Morales, they usually determined to make partial closures to keep away from dangers, as a result of the rains don’t cease within the sector.

“Because of the heavy rains that hit the division, landslides have been recorded from km 60 to 61 and in prevention of attainable accidents, the Departmental Coordinator for Catastrophe Discount (CODRED), informs us {that a} momentary closure is established whereas the cleansing duties of the Chimaltenango bypass,” says a press release from the Departmental Authorities of Chimaltenango.

The doc provides that “customers’ understanding is requested, since this resolution is made to forestall accidents on mentioned stretch of street, and it’s also instructed to take different routes to keep away from setbacks.”

“Two lanes have been enabled within the space, Provial, PMT of Chimaltenango, El Tejar, San Andrés Itzapa and the Site visitors Division of the PNC of Chimaltenango are within the space calling for prevention and to flow into with warning,” Conred detailed.

The measure was taken as a result of this Tuesday a brand new landslide affected the passage on the Chimaltenango bypass, the place the rain triggered two lanes, from the capital to the west, to be blocked at kilometer 60.5.

At that very same level, one other landslide was recorded final Monday, nevertheless it was eliminated by the authorities.

A heavy transport pilot who was passing by mentioned that it’s unlucky that each time it rains there are landslides on that street.

“The Ministry of Communications ought to now take motion on the matter as a result of, God forbid, there might possibly be a much bigger landslide and if vehicles cross by there might possibly be human losses,” mentioned the pilot.

Q528.6 million street that crumbles with the rain

A freeway that untangles visitors on the Inter-American Freeway, inaugurated in 2019 by former President Jimmy Morales (2016-2020) and price US$68.3 million (Q528.6 million), collapses with the rains and exemplifies corruption within the nation, in keeping with a report by the EFE company.

The 14.5 kilometers of 4 lanes that have been deliberate to ease the passage of the freeway, known as the “Chimaltenango bypass,” have been boasted in April 2019 by Morales as a “mega venture” and “historic milestone” to profit greater than six million Guatemalans.

However two years later, the street suffers severely in winter and is virtually allergic to the rains, as well as, the price of the funding grew by 1 / 4 of its finances.

The primary rain of the 12 months by which Morales inaugurated the stretch was the prologue to a novel with out an finish, with steady floods and landslides which have stripped a controversial street of slopes with concrete coatings that crumble in a number of sectors with every vital accumulation. of water.

Un megafraud

In July 2020, 17 individuals have been arrested for technical, monetary and administrative anomalies across the development of the freeway, however three months later, in October, the decide accountable for the method, Mynor Moto, dominated that there was no advantage in opposition to them. the accused and launched them.

Within the judicial course of, the previous Minister of Communications of the Jimmy Morales Administration, José Luis Benito, was linked to the alleged corruption plot.

Benito was additionally charged with the 2020 look of US$15.7 million in money in suitcases inside a residence underneath his alleged supervision.

All are accused of fraud in a development venture initially awarded to the corporate Constructora Nacional, Sociedad Anónima (Conasa) and which, following its disqualification as a consequence of different instances of corruption with the Authorities, handed to its subsidiary Renova.

Along with the landslides on the Chimaltenango bypass, flooding can be reported. (Free Press Photograph: Víctor Chamalé)

Closure suggestion

The Conred beneficial on the finish of 2019 “that mitigation work be carried out to keep away from this kind of downside and on the time it was instructed that the passage be closed in that place.

The 2019 Conred analysis report, issued weeks following the primary landslides, maintained that “the lithological traits of the rocks within the space are made up of intercalations of basalt blocks, tephra and residual paleosols – volcanic-type soil.”

These supplies “have low cohesion and are extremely inclined to erosion and detachments upon contact with water,” he provides.


#partially #shut #Chimaltenango #bypass #due #hazard #landslides

Share:

Facebook
Twitter
Pinterest
LinkedIn

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.