The No. 2 unit of the No. 2 Nuclear Power Plant began its final overhaul on February 26. The original estimated construction period was 40 days. However, due to the recent major power outage and tight power supply, the No. 2 unit was decided to go into battle ahead of schedule. Yuanenghui said yesterday that it has received an application from Taipower to start the criticality following the overhaul of the nuclear No. 2 and 2 unit EOC-27. In addition, the Yuan Energy Association has organized an expert observation group to travel to Japan to learn regarding the plan of the Fukushima nuclear power plant in Japan to discharge tritium-containing waste water into the sea next year, so as to obtain first-hand information.
The Yuan Energy Council pointed out that in addition to reviewing the application documents submitted by Taipower Corporation, it also plans to go to the Second Nuclear Plant for enhanced inspection from March 25 to 30. The exact time will be adjusted according to the actual inspection situation to further confirm the unit. condition.
Yuanneng will further mention that following the document review and enhanced inspection are completed, the results of various inspections and enhanced inspections performed by Yuanneng Club during the overhaul period will be comprehensively reviewed to confirm that the on-site status of the unit meets the start-up requirements before the unit will be approved. Start running. In addition, in response to changes in the new crown pneumonia epidemic, the inspection and confirmation of the power plant will also be strengthened during the inspection period, and various epidemic prevention measures once morest the new crown pneumonia will continue to be implemented.
In addition, Japan’s Fukushima nuclear power plant plans to discharge tritium-containing waste water into the sea next year. It is expected that the diluted nuclear waste water from the Fukushima nuclear power plant will be discharged at a depth of 12 meters, regarding 1 km from the shore, and the discharge operation will last for 30 years. The Yuanneng Association has organized an expert observation group to visit Japan and set off on the 24th.
The Yuan Energy Council pointed out that the 8-member observation delegation entered the Fukushima Daiichi nuclear power plant yesterday morning. After listening to the briefing by the Tokyo Electric Power Company personnel, they also inspected and learned regarding the relevant facilities in the plant, including the multi-nuclear species removal equipment (ALPS), storage ALPS treatment K4 tank area of water and related equipment for water treatment; in the followingnoon, we will inspect the analytical laboratory in the factory and communicate with the on-site personnel.