Thanh Long Group Joint Stock Company (Thanh Long Group) has just won the bid to implement Package No. 7 Providing and transporting shaped steel columns for the section from ĐĐ to VT25 with the winning price of 80 billion VND. This is a bidding package to implement the 500kV Nam Dinh I – Pho Noi Thermal Power Line Project by the Northern Power Project Management Board as the bidding unit. Thanh Long Group has surpassed the joint venture of Song Da 11 Joint Stock Company and HDC Communications and Technology Joint Stock Company.
Thanh Long Group was established in October 2002 in Van Lam district, Hung Yen province. The business is represented by Mr. Vu Thanh Long. In the last days of January 2024, Thanh Long Group immediately won 4 bidding packages from the Northern Power Project Management Board.
These bidding packages are part of the Nam Dinh I – Pho Noi 500kV Power Plant Line Project (belonging to the component project of the 500kV Circuit 3 Line Project from Quang Trach – Pho Noi), invested to meet the area’s electricity needs. Northern region right in the dry season of 2024.
Besides package number 7, the remaining 3 packages approved by Thanh Long Group include package 10 VT69 to VT97; Pack 11 VT98 to VT121 and Pack 16 VT197 to VT205. The total value of all 4 bidding packages is 271 billion VND.
According to the announced decisions approving the contractor selection results, Thanh Long Group won the bid through domestic, online public bidding; Fixed price contract type. The contract implementation time is the same 105 days.
In addition, Thanh Long Group Joint Venture – T-D Investment Consulting Joint Stock Company is currently participating in bidding for 13 packages to supply and transport steel poles for 500kV line Quang Trach – Quynh Luu, Quynh Luu – Thanh Hoa. Each bidding package has an average value of regarding 50 billion VND.
The Thanh Long – T-D joint venture is not unfamiliar because it is the investor of the Red River Surface Water Plant project worth nearly VND 3,700 billion that is behind schedule.
On the other hand, contractor data shows that on July 2, 2021, the Central Power Corporation issued a warning notice, terminating the contract performance contract, and confiscating the contract performance guarantee. contract of Thanh Long Group Joint Stock Company due to violating the obligation to perform a contract to implement a package of supply and transportation of steel columns (Contract No. 2005G03-DX.HA-065/CPC-TL).
Specifically, Thanh Long Group provided documents for procurement of input materials 64 days later than the prescribed time; Documents showing the origin of raw materials do not comply with the provisions of the contract/contract appendix; Delivery delay more than 4 weeks according to contract regulations.
Before seamlessly winning the 4 packages mentioned above, Thanh Long Group’s first day of the year did not go smoothly when it lost the bid on package 15 from VT190A to VT196, worth 47.2 billion VND, in front of its main competitor, Song Da 11 Joint Stock Company. .