In the following points, we review the implementation position of the project:
1. The western part of the civil works of the project (The Tree Gardens – Al Messaha), which is being implemented by the consortium of “Arab Contractors – Petrojet – Concord – Hassan Allam.” The stations from the tree gardens to the shooting station in the entirety of the area were handed over to the contractor, and from the Al-Ahram station to the Al-Massaha station. Partially delivered.
2. Works of the eastern part of the civil works of the project (surface – Fustat). Works are being awarded to Orascom Contracting, where the technical examination has been completed and the financial examination is underway.
3. As for the electromechanical works, railways and the workshop, a contract was signed to implement the works with the union of “Mitsubishi / Orascom” companies, and the contract entered into force, and design work is currently underway, and the work of supplying mobile units has been awarded to Mitsubishi.
4. Japan has provided a grant to finance the study of extending the first phase of the fourth metro line to the city of Paradise in the south for a distance of 4.5 km on the surface to serve the sectors of the 6th of October City located south of the Bahariya Oasis Road.