Prime Minister: Handling the collusion of goods, raising the price of construction materials | Economy

Prime Minister Pham Minh Chinh concluded the meeting. (Photo: Duong Giang/VNA)

After inspecting, urging and grasping the actual situation at component projects of the East North-South Expressway project passing through the provinces of Ninh Binh, Thanh Hoa, Nghe An, and Ha Tinh, on the evening of May 28. 1 in Nghe An, Prime Minister Pham Minh Chinh had a meeting with ministries, branches and localities to review the implementation of projects.

Attending the meeting were Deputy Prime Minister, Minister of Natural Resources and Environment Tran Hong Ha; Minister of Planning and Investment Nguyen Chi Dung; Minister of Transport Nguyen Van Thang; Minister of Construction Nguyen Thanh Nghi; leaders of relevant ministries and branches and leaders of provinces with routes through; representatives of investors, design consultancy contractors, supervision contractors, construction contractors.

The North-South expressway construction project in the East, from Ninh Binh to Quang Tri, has a total length of 480.5km through the provinces of Nam Dinh (5.2km), Ninh Binh (24.5km). , Thanh Hoa (98.8km), Nghe An (87.9km), Ha Tinh (107.14km), Quang Binh (124.41km), Quang Tri (32.53km).

The construction of the expressway is divided into 10 component projects in 2 phases: the period 2017-2020 has a total length of 221.2km, including 5 component projects (1 PPP investment project and 4 investment projects). public private sector); The period 2021-2025 has a total length of 259.3km, including 5 public investment component projects through the provinces of Ha Tinh, Quang Binh and Quang Tri.

[Thủ tướng: Khai thác du lịch tại những nơi cao tốc đi qua có cảnh đẹp]

Scale of investment in the completion phase of 6 express lanes, phased investment in 4 lanes with a roadbed width of 17m.

At the meeting, the ministries, branches and localities reported that the basic projects are being implemented smoothly in terms of progress, site clearance, disbursement progress, and the supply of material mines.. ., especially following the close direction of the Government, the Prime Minister.

However, the progress of some projects is still slow, there are still some obstacles in site clearance in some locations, the granting of material mines is still confusing regarding procedures, some investors are confused due to the high price. Sliding construction materials prices, investment capital…

Accordingly, investors propose the Government, the Prime Minister and ministries and branches to consider allowing investors to enjoy the policy of price compensation due to construction price slippage as for public investment projects; value added tax refund. Investors and contractors asked the locality to make efforts to clear and hand over the project site.

Regarding the granting of construction material mines, the contractors request the concerned ministries and branches to provide specific instructions on the order of applying for the construction material mines according to the new regulations according to the Government’s resolutions; localities to support and supply mines with sufficient reserves and mining capacity and help compensate for mining site clearance.

Concluding remarks, Prime Minister Pham Minh Chinh emphasized that the inspection of highway construction projects in the early days of the year showed that the whole country was responding strongly, with the high determination of the whole government system. government, the entire army, and the whole people to realize the goal of developing transport infrastructure, including the construction of highways set out by the 13th Party Congress.

The Prime Minister welcomed the very active participation of ministries, branches and localities; the enthusiasm and support of the people for the projects.

For work Clearance, the people have been very supportive and ready to implement, the local government must take the lead and proactively implement it quickly. If there are problems, they should proactively coordinate with ministries and branches to solve them according to their functions, tasks and competence; if beyond their competence, promptly report and propose to competent authorities.

Autumn: Expenses for the development of the cave, the price and the material for the image of him 2Prime Minister Pham Minh Chinh inspects the Bai Vot-Ham Nghi expressway project, the section through Can Loc district, Ha Tinh province. (Photo: Duong Giang/VNA)

For construction materials, the Prime Minister requested ministries, especially localities, to coordinate and review the work of mining and exploiting materials to serve this particularly important and meaningful project.

The Prime Minister asked the Ministry of Public Security to investigate and strictly handle according to law, the fact that organizations and individuals are granted construction material mines but colluded to hoard goods, raise prices, affecting the implementation of construction materials. project.

Ministries, branches, localities, contractors, investors, especially the heads, must take the lead in close coordination, regularly discuss when there is a problem and have to deal with it completely; The parties must create favorable conditions for each other in project implementation.

Prime Minister Pham Minh Chinh noted the phenomenon of subdivided bidding packages, increasing procedures, making it difficult to coordinate and articulate in construction implementation; Consulting and design work must end fragmentation, ensure objectivity, transparency, and avoid negativity.

“The spirit is that everything is solvable; Ministries, branches and localities must find a way out for problems, not to be stuck in traffic for a long time,” the Prime Minister directed.

The Prime Minister also noted that ministries, branches, localities, consultancy, design and supervision contractors must take the quality of the work as the top priority; ensure progress; not to charge unreasonable prices; ensure safety; ensuring art techniques, environmental hygiene, ensuring landscape; anti-corruption, negative; once morest bid collusion, bid sale; ensure the lives of workers.

The head of the Government directs ministries, branches and localities to urgently develop relevant plannings, open intersections and create new development spaces, with the motto “cross rivers, bridge, cross mountains, cut mountains”. , through the field, then pour the land, to build the shortest and straightest route possible, not following the old route and residential areas.”

In addition, urgently organize resettlement for the people to ensure the right policy, with the goal that the material, spiritual and employment life of the displaced people must be higher than the old place of residence and higher than before.

Regarding public-private cooperation in the construction of roads, the Prime Minister emphasized that the interests of the State, people and businesses must be harmonized. On that basis, ministries, sectors and investors must work together to calculate the best possible plan for implementation.

In particular, the Prime Minister requested the Ministry of Public Security to investigate and strictly handle according to law, organizations and individuals that are granted construction materials mines but colluded to hoard goods, raise prices, and affect the situation. implementing projects.

Previously, along with the inspection at Mai Son-National Highway 45, Dien Chau-Bai Vot projects, Prime Minister Pham Minh Chinh and the delegation inspected, visited, congratulated the new year, gave encouragement gifts. officials and workers participating in the Bai Vot-Ham Nghi expressway project in Son Loc commune, Can Loc district, Ha Tinh province under the East North-South expressway project phase 2.

The expressway project of Bai Vot-Ham Nghi section is regarding 35.28km long; total investment over 6,000 billion. Up to now, Ha Tinh province has handed over over 84.34% of the site to the investor to implement the project. The project was started with 12 other projects in the country on January 1, 2023.

Here, the Prime Minister requested Ha Tinh province to prioritize the supply of raw materials for the project; make every effort to complete the site clearance to implement the project on schedule, ensuring quality.

Regarding the resettlement of households within the project scope, the Prime Minister requested the local authorities to handle this work well, especially thoughtfully handling the relocation of graves; arrange adequate technical and social infrastructure in the resettlement area.

At the construction site, the Prime Minister gave gifts to resettled households; Hope the province soon arranges accommodation for displaced people to stabilize their lives. People expressed their joy, ready to give up land for the project, and hope the province will soon pay attention to arrange new accommodation.

During the business trip, Prime Minister Pham Minh Chinh and his delegation offered incense and flowers to commemorate the heroic martyrs and young volunteers who died in the resistance wars to save the country at the national historical relic site. special Fork copper fortuneHa Tinh.

The Prime Minister and his delegation offered incense and laid wreaths at the Memorial Hall of Youth Volunteer Martyrs – where more than 4,000 young volunteer martyrs are registered throughout the country and the graves of 10 female heroic martyrs. heroically sacrificed at Dong Loc T-junction.

Before the heroic spirits of heroes and martyrs, the Prime Minister and the delegation respectfully bowed and expressed their infinite gratitude for the great merits of his father’s generations for the cause of national liberation and reunification. water./.

Pham Tiep (VNA/Vietnam+)

Leave a Replay