Perintha on Perunpilav-Nilanpur State Highway Road: Updates, Progress, and Blacklisting of Contractors

2023-08-23 20:59:00

Perinthalmanna: Perintha on Perunpilav-Nilanpur State Highway Road from Pulamanthol to Melatoor in Lmanna mandal. Defendant and First Defendant State for subverting the Nardharana project Govt. and complete the work on time. Blacklisting of illegal contractors Mennum Najeeb Kanthapuram MLA demanded in the press conference.

The work of Pattanpi Road started during the time of the 1st Pinarai government. . Included in the Rebuild Kerala Initiative scheme before 29 September 2020 Pravrthi was inaugurated by Khyamantri Pinarai Vijayan.

After two years and seven months of operation which started on January 20, 2021, 52 It is just enough to complete the percentage. This is under the supervision of Public Works Department and Govt. For example.

The work has dragged on for 18 months. 144 crore project to assess progress The concerned departments are responsible for the steering committee. Failure to appreciate Vrithi’s progress is a failure.

The Minister of Public Works Department was contacted regarding the issue of this road. I have seen it many times. I met the officials of Thiruvananthapuram several times. Apart from this, the meeting of the employees has been held 14 times.

The issue was also raised in the legislature. Hundreds of patients in the hospital town of Perinthalmanna is arriving. Due to the road collapse, even the patients were rushed to the hospital on time. Can’t hit.

A major road connecting Thrissur, Palakkad and Malappuram districts. Thousands of vehicles are purchased by the Divasena in this way. going to The assurances given by the contractors in the meetings are never fulfilled. no

Contract company blacklisted for misleading people Najib said that the work should be assigned to the contractors instead of anything else. Kanthapuram MLA said.