(PLO)- Vice Chairman Bui Xuan Cuong asked the People’s Committee of Thu Duc City and districts to set up a working group to review long-running projects and cases that caused irritation. One of the projects being “pushed” to be solved is Vinh Loc Residential Area.
Vice Chairman of Ho Chi Minh City People’s Committee Bui Xuan Cuong has just directed the review of difficulties and problems of long-running projects and cases.
Mr. Bui Xuan Cuong asked the People’s Committee of Thu Duc City and districts to set up a working group to review long-running projects and cases that caused irritation; proactively coordinate with relevant departments, branches and units to promptly assess and propose solutions to remove difficulties and obstacles in the implementation process.
Among the long-term projects, Vinh Loc Residential Project, located in Binh Hung Hoa B Ward, Binh Tan District currently has many problems and backlogs. Vice Chairman of the City People’s Committee assigned the Department of Home Affairs to study and advise the City People’s Committee to establish an interdisciplinary working group to deal with the problematic contents of this project.
At the same time, the Department of Planning and Economics, the Department of Natural Resources and Environment, the Department of Construction, and the Department of Finance were assigned to urgently support and guide Binh Tan People’s Committee, the investor is District 5 Public Service Co., Ltd. to deploy and push forward. fast implementation.
The Vinh Loc residential area project was approved by the Prime Minister in 1999. After more than 20 years, following 4 terms of the National Assembly, the project might not be completed. Up to now, 95% of compensation has been made with Vinh Loc residential area project, and 300 households have not yet been settled. The difficulty of this project is that the land acquisition campaign faces many difficulties.
Previously, Binh Tan District People’s Committee and District 5 Public Service One Member Limited Liability Company sent the City People’s Committee a plan to coordinate and support the Investor to accelerate the implementation of this project. Among them, the issuance of land use right certificates to households is one of the contents that need to be accelerated.
In November 2022, Chairman of Ho Chi Minh City People’s Committee Phan Van Mai had a meeting with Binh Tan District People’s Committee. Many opinions regarding hanging projects in the area were given by the local government for departments and branches of the city to discuss and remove.
The head of the city government at that time considered it necessary to set up a working group to solve the outstanding problems of suspended projects.
The Steering Committee will focus on 2-3 months to review the issue groups; 2-3 months planning to solve each problem and how to solve suspended projects. Since then, it has been elevated to the city’s steering committee to direct the outstanding issues of suspended projects.
Ho Chi Minh City studies to set up a Steering Committee to solve the backlogs of suspended projects
(PLO)- Chairman of the Ho Chi Minh City People’s Committee Phan Van Mai said that there will be a study and establishment of a working group to solve suspended projects in each district, towards building a Steering Committee to solve the backlog of projects. suspended sentence.