Completion of 99.5% of the total work of the Grand Egyptian Museum project


Written by Muhammad Asaad

Thursday, February 16, 2023 04:53 PM

Construction work and final fit-outs continue The Grand Egyptian Museumwhich began in the trial operation of some services, and we review in the following lines the percentage of implementation, some of which have reached their full completion, according to the data of the Ministry of Tourism and Antiquities:

  • Completion of 99.5% of the total work completion at the site in general.

  • 100% completion of the structural structure, floors, surrounding internal roads, green spaces, the facade overlooking the pyramids, and the internal facade.

  • Completion of 90% of the electromechanical systems.

  • Completion of 97% of the smart communication and insurance systems.

  • The percentage of completion in the Khufu Boat Museum has reached 100% for the external facades and 70% for the interior finishes and display.

  • 100% completion of the interior hall, 99.9% of Tutankhamun Hall, and 99% of the artifact placement process.

  • Completion of 100% of the engineering works and 87% of the museum display works.






Leave a Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.