Asunción, IP Company.- The Minister of Public Works, Claudia Centurión, accompanied by President Franco’s mayor, Roque Godoy Jara, supervised the progress of the work on the Japanese Metropolitan Hall (CMDE), which might finish this 12 months.
The civil and street works that make up the Japanese Metropolitan Hall (CMDE) proceed to progress favorably, with completion anticipated for August and October of this 12 months.
Throughout the tour, the top of the Ministry of Public Works and Communications (MOPC) emphasised the significance of the progress achieved and expressed her hope that this 12 months each entry to the bridge from the Paraguayan and Brazilian sides might be enabled.
“We hope that Brazil, in an identical scenario, can have entry to the bridge operational and that this infrastructure can be utilized by all residents,” declared Claudia Centurión.
For his half, the mayor thanked the go to and the work carried out, highlighting the significance of this work for the neighborhood of Presidente Franco.
“I’m very grateful for the go to and the work that’s being performed, which reveals the priority for this vital work for our residents. I hope that, because the minister mentioned, the bridge entry works can be accomplished by October, coinciding with the anniversary of our metropolis,” she added.
In regards to the progress of the works
As for the first zone, a progress of fifty% is reported with completion projected for August 2024, whereas the Cargo Terminal of the Nationwide Administration of Navigation and Ports (ANNP), positioned 1,800 meters from the Integration Bridge , reveals a progress of 42%, with supply estimated for October 2024.
The Presidente Franco city lot, important for the street connection to the brand new border crossing, is in a sophisticated state, with 89% progress and its completion is estimated for October 2024.
As soon as this sector is accomplished, it would facilitate the provisional reference to the Paraguayan street community, pending the 2 rural heaps below building, with progress of 44% and 60%, respectively.
CMDE Description
The CMDE includes a set of civil and street works geared toward bettering entry to the not too long ago accomplished Integration Bridge, which connects the cities of Presidente Franco and Foz de Yguazú, Brazil.
Financing, as much as USD 212 million, comes from the Growth Financial institution of Latin America (CAF), with the Ministry of Public Works and Communications (MOPC) main this undertaking.