2023-09-15 14:48:00
This Monday, September 18, work to repair the surface of the N82/Arlon bypass will begin near the Hydrion zone. They will only concern the tracks towards Virton. The operations will modify traffic conditions there for a week.
The work will make it possible to renew the upper layers of the N82 road surface at the Hydrion zone over 300 meters towards Virton.
Changes to traffic conditions
From Monday September 18 to Monday September 25, on the N82/rue d’Arlon one lane will be closed to traffic for several hundred meters towards Virton. The maximum speed will be limited to 50 km/h.
This project represents a budget of nearly €97,000 excluding VAT financed by Sofico, the project owner. It will be carried out in collaboration with its technical partner: SPW Mobilité et Infrastructures, project manager. The company Socogetra was appointed by public contract to carry out this work.
1694837062
#Arlon #work #Hydrion #zoning #road #Virton #begins #Monday