The Replacement work for the sewer collector on 9 de Julio street, between España and Avenida Roca that began last Friday generates more than one headache for Roca drivers. The deployment of the works entails street closures and this Wednesday affects Avenida Roca.
Traffic remains closed in the microcenter, on the street Avenida Roca and Tucumán on the hand that goes south, towards 9 de Julio, where the work is concentrated this morning. The operators of Aguas Rionegrinas are carrying out a ditching.
The company contracted by ARSA is Arideros. The work contemplates the installation of 123 new meters of sewage collector, with the respective replacement of the pavement in the affected sector and will imply a provincial investment of $18,901,858.
It is recommended to neighbors travel with caution through this sector of the city since the works will continue for several more days.
Other sewer works in Roca
Then, the replacement of the sewage collector will begin. Roca Avenue between July 9 and May 25, for which the contracted company is Rimsol. It will start the tasks once the current one is finished, on July 9.
It is also taking place Replacement of the sewer collector in Jujuy street, between Antártida Argentina and Viedma. The Rimsol company has already carried out the perforations and the extension of the bypass, and they are working to seal the collector.
Other works already finished are the Roca Avenue between Artigas and Alsina, Buenos Aires Street between Chulavista and Brasil, Urquiza between Padre Nazario and Villegas, Uruguay Street between Belgrano and Buenos Aires and finally, España Street between Alsina and Artigas.