Long An proposes provinces to pay attention and prioritize materials for Belt 3 project

(PLO)- The People’s Committee of Long An province has proposed that the People’s Committee of Ho Chi Minh City summarize and report to the Prime Minister to direct the leaders of the provinces with material mines to pay attention, support and prioritize materials for the Ring Road 3 project. Ho Chi Minh City.

The Ring Road 3 project in Ho Chi Minh City has a length of 76.34 km, passing through the territory of Ho Chi Minh City, Dong Nai, Binh Duong and Long An, with a total investment of 75,378 billion VND.

However, up to this point, the Ministry of Natural Resources and Environment has not approved the appraisal results of the environmental impact assessment report; There are no guidelines for implementation of documents and procedures for mining construction materials to proactively source materials for construction.

The Ring Road 3 project in Ho Chi Minh City passing through Long An province has a length of 6.37 km, with a total investment of 4,208 billion VND. Up to this point, the district has issued 319 land acquisition notices out of a total of 380 affected households.

Ground clearance milestones of Ring Road 3 have been planted in Ben Luc district. Photo: HUYNH DU

It is expected that in June, the locality will hand over 70% of the site to the construction unit to start construction in the beginning of the third quarter. However, the implementation of documents and procedures for mining materials encountered many difficulties due to obstacles in the provisions of the mineral law, investment law and land law.

According to Mr. Dang Hoang Tuan, Director of Long An Department of Transport, said: “The meeting between the departments and branches of Ho Chi Minh City, Dong Nai, Binh Duong and Long An found that the source of sand filling materials is very difficult, need coordination and support from the provinces of the Mekong Delta, namely Tien Giang and Vinh Long, in the coming time, the leaders of the provinces will work with the provinces of the Mekong Delta to have material support. Whether”.

Long An proposes provinces to pay attention and prioritize materials for the 3rd Ring Project. Photo 2

People in Ben Luc district agreed with the Ring Road 3 project and proposed to speed up the project. Photo: HUYNH DU

Ring Road 3 in Ho Chi Minh City is a very important project for Long An and the provinces located in the southern key economic region. Therefore, right from the beginning of 2023, Mr. Nguyen Van Duoc – Secretary of the Long An Provincial Party Committee led the field survey mission and directed the relevant sectors to carry out the tasks as quickly and as possible.

Long An proposes provinces to pay attention and prioritize materials for the 3rd Ring Project
Secretary of the Provincial Party Committee Nguyen Van Duoc (white shirt pointing) surveys at the Ring Road 3 project. Photo: HUYNH DU

According to the Secretary of the Long An Provincial Party Committee, the units need to complete the site clearance work in the second quarter of 2023 and will start construction at the beginning of the third quarter. Long An is working closely with Ho Chi Minh City, Dong Nai and Binh Duong to complete pre-feasibility documents to submit to the Government and National Assembly as soon as possible.

In terms of capital, in addition to the support from the Central Government, the part of capital under the responsibility of Long An will ensure enough money to carry out the site clearance as soon as possible to start construction and complete the entire project by 2026.

Ho Chi Minh City issued an urgent dispatch requesting to speed up the 3rd belt project

Ho Chi Minh City issued an urgent dispatch requesting to speed up the 3rd belt project

(PLO)- In order to speed up the implementation of the investment project to build Ring Road 3 in Ho Chi Minh City, the City People’s Committee has given many instructions.

HUNG DUONG