Construction of My Thuan 2 bridge throughout Tet

(PLO)- In the Lunar New Year 2023, dozens of workers are still enthusiastically working at the main pillar of My Thuan 2 bridge to ensure that the project is completed on schedule by the end of 2023.

During the Lunar New Year of the Rabbit in 2023, when everyone was gathering with their families, dozens of workers and engineers were still hard at work executing parts to ensure the completion of My Thuan 2 Bridge by the end of this year. .

Hoang Dang Hau – Engineering in charge of construction (Trung Nam E&C Joint Stock Company) said that the construction site currently has 30 workers and a force of engineers, operating and working throughout Tet to complete the last part of the T16 pillar. .

My Thuan 2 Bridge gradually completed

Construction of My Thuan 2 bridge through Tet photo 2
Construction of My Thuan 2 bridge through Tet photo 3
Construction of My Thuan 2 bridge through Tet photo 4

Exciting working atmosphere at My Thuan bridge construction site 2 days of Tet

After Tet, when the workforce is reinforced once more, the progress will be fast. After completing Pillar 16, will proceed to install beams and pull cables. Workers are arranged to work 2 shifts to ensure the work as planned.

On the contractor’s side, there are also reasonable remuneration policies and care for workers who work throughout Tet.

Construction of My Thuan 2 bridge through Tet photo 5
Construction of My Thuan 2 bridge through Tet photo 6
Workers are still hard at work on the construction site of My Thuan 2 bridge

The construction investment component project of My Thuan 2 bridge and the road leading to the two ends of My Thuan 2 bridge spanning the Tien River, connecting Tien Giang province with Vinh Long has a total investment of more than 5,000 billion VND.

The project started on March 16, 2020. According to Project Management Board 7, following more than 2 years of construction, the project has reached the progress of 70.73%, exceeding the plan by 2.07% (as of January 15).

Construction of My Thuan 2 bridge through Tet photo 7

The part of turret 16 is almost entering the final stage

Construction of My Thuan 2 bridge through Tet photo 8

Tower 15 on the shore of Vinh Long

Construction of My Thuan 2 bridge through Tet photo 9

Below are many means of gathering equipment for construction work

According to the plan, the project will be completed by the end of 2023. My Thuan 2 Bridge plays an important role, when completed, it will connect the My Thuan – Can Tho expressway, thereby connecting the entire highway from Ho Chi Minh City. to Can Tho City.

The project has 5 bidding packages, of which 1 package was completed by the end of 2021; The remaining bidding packages are still being implemented and guaranteed, ahead of schedule.

Construction of My Thuan 2 bridge through Tet photo 10

Workers take a lunch break following a hard day’s work

Construction of My Thuan 2 bridge through Tet photo 11

The pier on the shore of Vinh Long

Construction of My Thuan 2 bridge through Tet photo 12

When completed, My Thuan 2 Bridge will connect My Thuan – Can Tho Expressway, thereby connecting the entire highway from Ho Chi Minh City to Can Tho City.

In which, the main package XL.03B (Construction of piers from T14 to T17) and the structure on the main span of the cable-stayed span; riverbank reinforcement embankment; road traffic safety system; lighting system exceeded the plan 4.23%

Construction of My Thuan 2 bridge through Tet photo 13

Currently, the contractor is implementing 3 construction steps to ensure the completion of the assigned schedule

Pillars T15, T16 are entering the final stage of burning completion.

The main span of the cable-stayed span has also been constructed from August 19, 2022 and it is expected that October 30, 2023 will complete 16 main span casting segments on each tower.

Construction of My Thuan 2 bridge through Tet photo 14

The cables have been transported to the construction site

Construction of My Thuan 2 bridge through Tet photo 15
Construction of My Thuan 2 bridge through Tet photo 16
Construction of My Thuan 2 bridge through Tet photo 17

After completion of Pillar 16, beams and stay cables will be installed

Construction of My Thuan 2 bridge through Tet photo 18

My Thuan 2 Bridge crosses the Tien River, parallel to My Thuan 1 Bridge, which is 23 years old

In the coming time, the contractors will carry out the construction of the upper structure: The production of the casting vehicle has been basically completed, it is expected to be installed in January 2023 to construct the K2 beam block.

The guide pipe has been moved to the construction site. 61.8% of cable-stayed cables and accessories have been delivered to the construction site, the remaining volume will be delivered in January.

First cable-stayed cable stretch My Thuan 2 . bridge

First cable-stayed cable stretch My Thuan 2 . bridge

(PLO)- The first cable-stayed cable of My Thuan 2 bridge has been stretched following 33 months of construction

Leave a Replay