The agenda passed with 94.5% of the participating members in favor
(Seoul = Yonhap News) Reporter Hong Guk-ki = As the conflict between the union and the construction group (Hyundai E&C, HDC Hyundai Development, Daewoo E&C, and Lotte E&C) is intensifying over the reconstruction of Dunchon Jugong (Olympic Park Foreon) in Gangdong-gu, Seoul On the 16th, the side passed the agenda to cancel the resolution of the extraordinary general meeting of the association related to the contract to increase the construction cost in the past with the construction team.
The union held a regular general meeting at the Northeast Middle and High School in Dunchon-dong on the same day and voted on the agenda to cancel the resolution to change the construction contract at the extraordinary general meeting held on December 7, 2019. As a result, 4 out of 4,822 people in attendance (including written resolution) It was revealed that 1,558 people cast in favor (94.5% of the votes in favor).
The majority of union members expressed their opposition to the contract to increase the construction cost by regarding 560 billion won in June 2020, which is the cause of the conflict between the current union executive and the construction team.
The former chairman of Dunchon Jugong held an extraordinary general meeting of union members in December 2019 due to the advancement of materials and design changes, and in June 2020, the following year, the construction team and the construction cost increased from 2.6708 trillion won to 3.2294 trillion won. signed a contract
However, the executive department of the new association is adhering to the position that it cannot accept the contract between the construction group and the previous association, such as the dismissal of the president at the time, as there are many legal and procedural problems.
On the other hand, the construction team is of the opinion that there is no problem with the change of the construction contract at that time, as it passed the resolution of the general meeting of the association and received approval from the competent ward office.
The conflict between the two sides running parallel was not resolved, and the construction team completely halted the construction as of 00:00 the previous day, saying that it might no longer carry out traumatic work worth regarding 1.7 trillion won.
The union’s position on this is also strong.
Apart from the cancellation of the resolution related to the increase in construction cost on that day, on the 21st of last month, a lawsuit was filed with the Seoul Eastern District Court to nullify the contract to change the increase in construction cost.
In particular, if the construction team’s construction suspension period lasts for more than 10 days, the union is in a state of counterattack to push forward until the contract is terminated.
“At today’s general meeting, the majority of union members expressed their opinion that the contract to increase construction cost is a contract with legal and procedural flaws,” said an official from the union’s executive department.
Dunchon Jugong Reconstruction is considered to be the ‘largest reconstruction project since Dangun,’ which involves demolishing 5,930 households and building the highest 35-story building, 85 buildings, and 12,32 households. So far, the completion rate has reached 52%.
Report on Kakao Talk okjebo