Vienna (OTS) – On Tuesday, August 22nd, 2023, the city of Vienna – road administration and road construction will start with roadway repair work and the erection of tree screens in Ketzergasse in the 23rd district. The renovation work on the roadway is necessary due to excavation work by building services and time damage and is being carried out in the section between Franz-Lehar-Gasse and Brunner Straße. In addition, in the area between Karl-Sarg-Gasse and Brunner Straße, a total of 26 tree pits will be erected, equipped with automatic irrigation and trees will be planted.
traffic measures
Ketzergasse is a one-way street from Brunner Strasse to and in the direction of Manngasse. The diversion in the direction of Brunner Strasse is via Perchtoldsdorfer Strasse, Breitenfurter Strasse, Rudolf-Waisenhorn-Gasse, Seybelgasse and An den Steinfeldern. Bus line 61B in the direction of Vösendorf-Siebenhirten will be diverted via the same route as private transport. The existing stops of bus route 64A will be approached.
- Location of the construction site: 23., Ketzergasse between Karl-Sarg-Gasse and Brunner Straße
- Start of construction: August 22, 2023
- Planned end of construction: November 17, 2023
For more information, visit wien.gv.at/verkehr/strassen and wien.gv.at/verkehr/baustellen or on +43 1 955 59 – road and traffic information line.
Questions & contact:
Erwin Forster
City of Vienna – Road Administration and Road Construction
public relation
Phone: +43 1 4000-49811
Mobil: +43 676 8118 49811
E-Mail: erwin.forster@wien.gv.at
Silvia Aigner
City of Vienna – Road Administration and Road Construction
public relation
Phone: +43 1 4000-49812
Mobil: +43 676 8118 49812
Email: silvia.aigner@wien.gv.at
1692378199
#23rd #district #roadway #rehabilitation #greening #measures #Ketzergasse #section #PID #press